T1 - Application and evaluation of ground surface pre-grouting reinforcement for 800-m-deep underground opening through large fault zones
AU - Qian, Deyu
AU - Zhang, Nong
AU - Zhang, Mingwei
AU - Shimada, Hideki
AU - Cao, Peng
AU - Chen, Yanlong
AU - Wen, Kai
AU - Yang, Sen
AU - Zhang, Nianchao
PY - 2017/7/3
Y1 - 2017/7/3
N2 - Faults are complex geological conditions that are commonly encountered during underground excavation. Many support schemes, such as using a single pilot heading method and 30-m-long borehole pre-grouting, have been implemented during the pilot excavation of an 800-m-deep underground opening that passes through large fault zones in East China. However, various geo-hazards, including groundwater inrush, debris flow, and roof collapse, are still occurring, which seriously threaten tunneling safety. To eliminate the geo-hazards and ensure tunneling safety, ground surface pre-grouting (GSPG) was proposed and implemented for the first time to reinforce the regional engineering rock mass for this proposed 800-m-deep underground opening passing through large fault zones. The minimum grouting pressure of GSPG at a depth of 800 m below the surface is put forward based on hydraulic fracturing theory, providing valuable guidance for GSPG engineering practice. Engineering practice demonstrates that GSPG eliminates geo-hazards, improves the objective rock mass stability, and ensures tunneling safety. Field measurements indicate that the displacement velocity of the surrounding rock shows an obvious fluctuation response under the influence of GSPG, and the impact of GSPG on the stability of the 800-m-deep underground opening that has been excavated dramatically decreases as the distance from the grouting borehole increases. Moreover, there is a strong negative exponential correlation between the maximum velocity of deformations and the distance from the grouting borehole. In addition, the safe distance underground during GSPG is greater than 137 m.
AB - Faults are complex geological conditions that are commonly encountered during underground excavation. Many support schemes, such as using a single pilot heading method and 30-m-long borehole pre-grouting, have been implemented during the pilot excavation of an 800-m-deep underground opening that passes through large fault zones in East China. However, various geo-hazards, including groundwater inrush, debris flow, and roof collapse, are still occurring, which seriously threaten tunneling safety. To eliminate the geo-hazards and ensure tunneling safety, ground surface pre-grouting (GSPG) was proposed and implemented for the first time to reinforce the regional engineering rock mass for this proposed 800-m-deep underground opening passing through large fault zones. The minimum grouting pressure of GSPG at a depth of 800 m below the surface is put forward based on hydraulic fracturing theory, providing valuable guidance for GSPG engineering practice. Engineering practice demonstrates that GSPG eliminates geo-hazards, improves the objective rock mass stability, and ensures tunneling safety. Field measurements indicate that the displacement velocity of the surrounding rock shows an obvious fluctuation response under the influence of GSPG, and the impact of GSPG on the stability of the 800-m-deep underground opening that has been excavated dramatically decreases as the distance from the grouting borehole increases. Moreover, there is a strong negative exponential correlation between the maximum velocity of deformations and the distance from the grouting borehole. In addition, the safe distance underground during GSPG is greater than 137 m.
KW - Fault zones
KW - Geo-hazards
KW - Ground surface pre-grouting
KW - Grouting pressure
KW - Underground opening
UR - https://www.scopus.com/pages/publications/85021694290
U2 - 10.1007/s12517-017-3052-7
DO - 10.1007/s12517-017-3052-7
M3 - Article
AN - SCOPUS:85021694290
SN - 1866-7511
VL - 10
JO - Arabian Journal of Geosciences
JF - Arabian Journal of Geosciences
IS - 13
M1 - 285
ER -